AS/NZS 3000-2007 AS/NZS 3000-2018 V6

The Wiring Rules: The Master Standard

AS/NZS 3000, commonly known as the Wiring Rules, is the foundation of all electrical installation work in Australia and New Zealand. For solar PV, it governs every aspect of the AC-side installation and — together with AS/NZS 5033 — the DC-side as well. The 2018 version (V6) is the current edition and supersedes the 2007 edition for all new work.

As a licensed installer, you are legally required to comply with AS/NZS 3000. Non-compliance constitutes an unsafe installation and a breach of the electrical safety legislation in each state and territory.

Key Chapters of AS/NZS 3000 Relevant to Solar

Chapter 2 — General Arrangement

  • Solar AC circuits must have a dedicated circuit from the switchboard

  • A lockable solar isolation switch (visible and accessible) must be installed at the switchboard

  • A dedicated solar generation meter or import/export meter must be provided in grid-connected systems

  • The solar circuit must be clearly labelled: "Solar PV System — Danger — Do Not Switch Off Without Isolating Solar Array First"

Chapter 3 — Selection of Wiring Systems

Circuit

Minimum Requirements

Wiring Rules Reference

DC array string cables

UV-resistant, 1000V DC rated, double-insulated (H1Z2Z2-K or equivalent)

As/NZS 5033 + Cl. 3.8

DC main cable (array to inverter)

As above; single-core cables in conduit or twin-core flexible

Cl. 3.8.4

AC inverter output to switchboard

As per AS/NZS 3008 cable selection; V-90 or V-75 acceptable

Cl. 3.8

Conduit in roof cavity

Non-metallic conduit must be UV-rated where exposed; max fill 40%

Cl. 3.10.2

Chapter 4 — Protection

The Wiring Rules require protection against:

  • Overcurrent (4.3) — string fuses or string CBs required when more than 2 strings are paralleled, per AS/NZS 5033

  • Electric shock (4.4) — RCD (residual current device) protection required for AC circuits. Note: DC circuits cannot be protected by standard AC RCDs; DC-capable RCDs or AFCI are required where mandated

  • Surge voltage (4.9) — SPDs required at the main switchboard. For solar, additional SPDs at the inverter DC input are required under AS/NZS 5033

  • Fire (4.10) — arc fault detection required in certain configurations. Wiring in concealed or inaccessible locations must use appropriate cable types

Chapter 5 — Earthing

The earthing requirements for solar AC circuits are the same as for any other sub-circuit: a continuous protective earth conductor from the switchboard to the inverter chassis. Critical points:

  • The inverter protective earth must connect directly to the main earth bar — not via another circuit earth

  • For transformerless inverters (the vast majority of residential inverters), the DC negative is typically bonded to earth inside the inverter — installers must not add an external DC negative earth bond

  • An isolating transformer between the inverter and grid allows an unearthed (floating) DC system — this configuration requires a Ground Fault Detection (GFD) device under AS/NZS 5033

Chapter 7 — Special Installations (Solar PV)

The 2018 edition of the Wiring Rules includes specific clauses for PV power supply systems (Section 7.3.5, referencing AS/NZS 5033 as the primary standard). Key requirements include:

  • Inverter must be CEC approved (listed on the CEC Approved Products list)

  • Maximum system voltage: 600 V DC for residential buildings; 1000 V DC for commercial (with enhanced safety measures)

  • Emergency shutdown provisions — a visible, lockable AC isolation switch accessible to emergency services

  • Labelling of all DC conductors, isolators, and junction boxes at installation

Common Wiring Rules Violations in Solar Installations

Violation

Risk

Standard Clause

Using AC-rated cable for DC string runs

Insulation breakdown — fire risk

Cl. 3.8 / AS 5033

No DC isolator at array (rooftop)

Inability to de-energise array for emergency

AS 5033 Cl. 4.3.4

Conduit not sealed at penetrations

Pest ingress, moisture, fire spread

Cl. 3.10.2.7

Missing solar generation meter

Non-compliance with network connection agreement

DNSP connection agreement

SPDs not installed

Inverter failure after any nearby lightning event

Cl. 4.9 / AS/NZS 1768

No isolation switch label

Firefighter confusion during emergency

Cl. 5.7.4 / AS 5033

Engr. Jason Morales — Founder, SolarEnergyPH

Keep Reading