Commissioning Is Not Optional

Commissioning is the systematic verification that the installed system operates correctly and safely before the client takes possession. It is required by AS 4777.1, the CEC Design and Installation Certificate process, and the DNSP grid connection agreement. A system that has been "turned on" is not commissioned — a system that has been tested, verified, documented, and signed off is commissioned.

Pre-Energisation Checks

  • All mechanical fixings confirmed — racking, panel clamps, conduit supports

  • All DC connectors fully mated (visual inspection + tug test)

  • All string polarities confirmed (voltmeter — positive to positive throughout)

  • Array insulation resistance tested: each string positive-to-earth and negative-to-earth (>1 MΩ per string)

  • String VOC measured and compared to calculated value (±5%)

  • AC cable insulation resistance tested

  • Earth continuity from inverter to main earth bar measured (<1 Ω)

  • RCD/RCBO trip time tested (<40 ms at 5× rated leakage current)

  • All labels confirmed in place and legible

Energisation and Functional Tests

  • AC isolation switch operated — confirm inverter shuts down

  • Inverter DC isolator opened — confirm inverter shuts down

  • Grid connection: inverter syncs to grid within manufacturer's specified time

  • Measured AC output voltage (228–232 V) and frequency (49.9–50.1 Hz)

  • Volt-Watt / Volt-VAR settings confirmed (per DNSP requirements)

  • Grid protection settings confirmed (voltage and frequency thresholds)

  • Anti-islanding test: open AC isolation switch with inverter running — verify trip within 2 seconds

  • For battery systems: charge and discharge cycle initiated; SoC display calibrated

Documentation

  • Commissioning test form completed with measured values

  • CEC Design and Installation Certificate signed and dated

  • CCEW (or state equivalent) issued

  • DNSP notification submitted

  • Owner handover completed (system operation, emergency isolation, maintenance requirements)

Engr. Jason Morales — Founder, SolarEnergyPH


Installation and safety requirements for PV arrays (AS 5033-2014) & Guide to solar safe installation
Installation and safety requirements for PV arrays (AS 5033-2014) & Guide to solar safe installation
A two-in-one reference covering PV array installation and safety requirements per AS 5033-2014, bundled with a practical safe solar installation guide — essential reading for solar installers, elec...
$9.99 usd

Philippines Solar PV Installation Guide 2026 — Based on Australian Standards
Philippines Solar PV Installation Guide 2026 — Based on Australian Standards
A complete technical reference for solar PV system installation in the Philippines — drawn directly from AS/NZS 4509.1:2009, AS 4777.1:2005, and AS/NZS 3000:2007, cross-referenced to PEC 2017 and D...
$9.99 usd

The Complete Solar PV Starter Kit for the Philippines
The Complete Solar PV Starter Kit for the Philippines
A free 4-part guide for Filipino homeowners and solar installers — system sizing, BOM template, ROI calculator, and quotation guide. Written by a Licensed Electrical Engineer.
$0.00 usd