Why Insulation Testing Is Critical for DC Solar
DC string cables run through environments hostile to cable insulation — UV exposure, rodent habitats, mechanical abrasion on roof edges, and thermal cycling every day. Insulation resistance testing (IR testing) with a megohmmeter detects deteriorating insulation before it fails completely, preventing ground faults, arc faults, and inverter damage.
Test Procedure for Solar DC Circuits
Isolate the inverter: Open the DC isolator and disconnect the inverter DC input — you will be applying test voltage to the inverter's terminals otherwise
Short the string: Short-circuit the positive and negative conductors of the string at the combiner box or at the array DC isolator (this tests both conductors together against earth simultaneously)
Apply test voltage: Use 500 V DC for systems up to 500 V DC; 1000 V DC for higher-voltage strings. Apply for a minimum of 1 minute to allow capacitive charging to stabilise
Record resistance: Read insulation resistance at 1 minute. Note if the reading is rising (good — capacitive stabilisation) or steady (acceptable) or falling (concerning — potential moisture ingress)
Acceptance Criteria
Condition | Minimum Acceptable Resistance |
|---|---|
New installation (new cables, dry conditions) | >10 MΩ per string (ideally >100 MΩ) |
Commissioned installation (operational) | >1 MΩ per string |
Wet or damp conditions (morning dew) | >100 kΩ — retest when dry before concluding fault |
Below 100 kΩ in dry conditions | Fault — locate and repair before commissioning |