Why Insulation Testing Is Critical for DC Solar

DC string cables run through environments hostile to cable insulation — UV exposure, rodent habitats, mechanical abrasion on roof edges, and thermal cycling every day. Insulation resistance testing (IR testing) with a megohmmeter detects deteriorating insulation before it fails completely, preventing ground faults, arc faults, and inverter damage.

Test Procedure for Solar DC Circuits

  1. Isolate the inverter: Open the DC isolator and disconnect the inverter DC input — you will be applying test voltage to the inverter's terminals otherwise

  2. Short the string: Short-circuit the positive and negative conductors of the string at the combiner box or at the array DC isolator (this tests both conductors together against earth simultaneously)

  3. Apply test voltage: Use 500 V DC for systems up to 500 V DC; 1000 V DC for higher-voltage strings. Apply for a minimum of 1 minute to allow capacitive charging to stabilise

  4. Record resistance: Read insulation resistance at 1 minute. Note if the reading is rising (good — capacitive stabilisation) or steady (acceptable) or falling (concerning — potential moisture ingress)

Acceptance Criteria

Condition

Minimum Acceptable Resistance

New installation (new cables, dry conditions)

>10 MΩ per string (ideally >100 MΩ)

Commissioned installation (operational)

>1 MΩ per string

Wet or damp conditions (morning dew)

>100 kΩ — retest when dry before concluding fault

Below 100 kΩ in dry conditions

Fault — locate and repair before commissioning

Engr. Jason Morales — Founder, SolarEnergyPH

Installation and safety requirements for PV arrays (AS 5033-2014) & Guide to solar safe installation
Installation and safety requirements for PV arrays (AS 5033-2014) & Guide to solar safe installation
A two-in-one reference covering PV array installation and safety requirements per AS 5033-2014, bundled with a practical safe solar installation guide — essential reading for solar installers, elec...
$9.99 usd

Philippines Solar PV Installation Guide 2026 — Based on Australian Standards
Philippines Solar PV Installation Guide 2026 — Based on Australian Standards
A complete technical reference for solar PV system installation in the Philippines — drawn directly from AS/NZS 4509.1:2009, AS 4777.1:2005, and AS/NZS 3000:2007, cross-referenced to PEC 2017 and D...
$9.99 usd

The Complete Solar PV Starter Kit for the Philippines
The Complete Solar PV Starter Kit for the Philippines
A free 4-part guide for Filipino homeowners and solar installers — system sizing, BOM template, ROI calculator, and quotation guide. Written by a Licensed Electrical Engineer.
$0.00 usd