Clint Brauer grew up on his family's Kansas farm. His dad sprayed the same chemicals every American farmer sprays. Years later: Parkinson's. Clint walked away from a tech career to build a different way. Today his company, Greenfield Robotics, runs a patented fleet of autonomous bots that slice weeds with centimeter precision, day or night, herbicide-free.
Greenfield is now opening shares to everyday investors under Reg A+. Reserve during Test the Waters and you lock in a 5% bonus that can grow to 20% the week the round goes live. The US has 250 million acres at stake.
Greenfield Robotics is Testing The Waters under tier 2 of Regulation A. No money or other consideration is being solicited, and if sent in response will not be accepted. No offer to buy the securities can be accepted and no part of the purchase price can be received until the offering statement filed by the company with the SEC has been qualified by the SEC. Any such offer may be withdrawn or revoked, without obligation or commitment of any kind, at any time before notice of acceptance given after the date of qualification. An indication of interest involves no obligation or commitment of any kind. “Reserving” shares is simply an indication of interest. There is no binding commitment for investors that reserve shares in this manner to ultimately invest and purchase the shares reserved of the company, or to purchase any shares of the company whatsoever.
What the System Owner Must Receive
A solar installation is not complete until the owner has received all documentation required by the CEC, the DNSP, and best practice. This documentation forms the basis for insurance claims, warranty claims, future maintenance, and system modifications. Failing to provide complete documentation is a breach of the CEC Code of Conduct.
Mandatory Handover Documents
Document | Provided By | Purpose |
|---|---|---|
Certificate of Compliance Electrical Work (CCEW) | Licensed electrical contractor | Legal compliance declaration — required by insurance and DNSP |
CEC Design and Installation Certificate | CEC-accredited installer | Required for STC rebate and grid connection |
As-built Single-Line Diagram | Installer | Documents actual system configuration for future reference |
Inverter installation and operating manual | Installer (from manufacturer) | Fault codes, settings, maintenance requirements |
Panel datasheet and warranty document | Installer | Warranty claim basis for panel performance defects |
System commissioning test results | Installer | Baseline performance data for future comparison |
Emergency isolation procedure (written) | Installer | Safety — the owner must know how to isolate the system |
Maintenance schedule | Installer | Defines inspection frequency, cleaning requirements, check items |
Monitoring platform login credentials | Installer | Access to system performance data and fault alerts |
Owner Training — What to Cover
Location of all isolation switches and their function
How to read the inverter display — generation power, daily yield, faults
How to use the monitoring app
What the normal daily generation pattern looks like (for their orientation and location)
When to call the installer vs when to call the DNSP
Engr. Jason Morales — Founder, SolarEnergyPH